Team capacity planner

Work out what a sprint is really worth in engineering days once meetings, on call, interviews, PTO, and a focus factor have all taken their cut. The whole formula is printed below and every default shows its source. Nothing is stored, no signup to see your result.

Your sprint

Working days, not calendar days. A two week sprint is 10.
Standups, planning, retro, review, one to ones, and the standing meetings nobody remembers agreeing to. Surveys of engineer meeting load cluster at 4 to 8 hours a week for individual contributors, higher for leads.
50%
How much of an on-call engineer's time the rotation eats. SRE practice treats a shift as interrupt-driven work rather than project work, and interruption research says the recovery cost is larger than the interruption. Default 50%.
Loops, debriefs, and prep. Count the panel's time, not the candidate's.
Counted for everyone on the team.
70%
The share of remaining time that turns into planned work. Standard agile guidance runs 60 to 80%. It absorbs context switching, unplanned support, and slack. If your team already estimates in ideal days, set this to 90 and read the note below about double counting.
Real capacity 0.0 0 hrs
Never reaches the board 0% of the sprint

Where the sprint goes

    Per engineer

    The same sprint divided by head count. PTO, interviews, and on call are entered as team totals, so they are spread evenly here; a real team carries them unevenly, and the engineer holding the pager is not the one taking PTO.

    Capacity per engineer by bucket

    Next six sprints

    Your current overhead held steady. Holidays and PTO are lumpy in real quarters, so treat this as the shape rather than the schedule.

    Capacity projected over six sprints

    Reclaim capacity, ranked

    Ranked by engineering days returned at your inputs, not by how good they sound in a retro. It is usually meetings. Anything that only moves an estimate rather than freeing real hours is listed last, however large it prices out.

      Exec summary (paste-ready)

      Next: if you are being asked to fund tooling out of the capacity you just measured, the AI coding tools ROI calculator runs the same honest math on the other side of the ledger.

      How the calculation works

      Every number above comes out of the formula below. There is no hidden multiplier and no backend. If you can read it, you can check it.

      gross_hrs        = team_size × sprint_days × 8
      meeting_hrs      = team_size × meeting_hrs_per_week × (sprint_days / 5)
      oncall_hrs       = oncall_count × sprint_days × 8 × oncall_drag%
      interview_hrs    = interview_hrs_total          (whole team, this sprint)
      pto_hrs          = pto_days_total × 8         (whole team, this sprint)
      holiday_hrs      = team_size × holidays_in_sprint × 8
      
      available_hrs    = gross_hrs − meeting − oncall − interview − pto − holiday
      focus_discount   = available_hrs × (1 − focus_factor)
      net_capacity_hrs = available_hrs × focus_factor
      net_eng_days     = net_capacity_hrs / 8
      
      breakdown %      = each bucket / gross_hrs      (the stacked bar)

      Three things in there are worth calling out, because they are where capacity math usually goes quietly wrong.

      The focus factor comes last. It applies to what is left after the named overheads, not to the gross sprint. Applying it to the gross number is the most common mistake in capacity spreadsheets, and it double counts: a 70% focus factor applied to a sprint that has already lost a quarter of itself to meetings is charging you for those meetings twice. Here every named cost is subtracted first, and the focus factor discounts only the remainder.

      On call is a percentage, not a person. An engineer on call is not gone, they are interrupted. The drag slider is how much of their sprint the rotation takes. Setting it to 100% would model a pager duty so bad the engineer does nothing else, which happens, but it should be a deliberate input rather than a default.

      Everything is one sprint's worth of hours. The meeting figure converts a weekly load to sprint length with sprint_days / 5, so a three week sprint carries three weeks of standups. Holidays reduce the sprint for everyone; the model does not then also reduce that day's meetings, which makes it very slightly conservative in holiday-heavy sprints.

      Not a sprint team? Nothing here needs a sprint. It works for any fixed planning window: put your window length in working days and read the answer the same way. If you have retired sprints in favour of continuous flow, this is still the honest denominator under your throughput.

      Where the defaults come from

      Every default is a starting point you should replace with your own data. Here is the source for each, so you can decide whether ours is reasonable for your team.

      InputDefaultWhy that number
      Sprint length10 working daysThe two week sprint is the most common cadence by a wide margin. Change it freely; the math does not care.
      Team size6A typical single-team size. No claim beyond that.
      Meeting hours per person per week6Surveys of meeting load for engineers cluster in the 4 to 8 hour range for individual contributors and run higher for leads and anyone with cross-team scope. Six is the middle of that band. Your calendar export will beat any survey, and it is a five minute job to pull.
      On-call capacity drag50%Site reliability practice treats an on-call shift as interrupt-driven work rather than project work, and interruption studies consistently find that recovering focus costs far more than the interruption itself. Fifty percent assumes a rotation that pages but does not burn. A quiet rotation might be 20%, a bad one 80%.
      Interview hours4 (team total)Roughly one loop's worth of panel time. Teams in an active hiring push routinely run several times this, which is exactly why it belongs in the model.
      PTO2 days (team total)A placeholder, not a claim. Use your actual approved time off; it is the one input you can look up exactly.
      Focus factor70%Standard agile guidance runs 60 to 80% and most teams that measure land near the middle. It absorbs context switching, unplanned support, and the slack a healthy system needs. It is the softest number here, which is why everything else is itemized rather than buried inside it.

      Sources are named rather than hot-linked because survey and vendor URLs rot; each is searchable by the description given (engineer meeting-load surveys, Google's site reliability engineering material on on-call, interruption and resumption-cost research, standard agile capacity guidance). This tool sells nothing and earns nothing from your answer.

      Questions people ask

      How do I calculate sprint capacity?

      Start from gross hours, which is team size times sprint working days times eight. Subtract the things you can name: recurring meetings, on-call drag, interview load, PTO, holidays. Then apply a focus factor to what remains, to cover the interruptions you cannot itemize. Divide by eight for engineering days. That is the whole method and it is the formula printed above. The part most teams skip is the subtraction step, which is also the part that makes the number defensible when someone asks why the team committed to less this sprint.

      What is a good focus factor in agile?

      Between 60 and 80% for most teams, and the honest answer is that you should measure yours rather than pick one. Take three completed sprints, compare planned work delivered against available hours, and use what you find. A team that keeps landing at 55% does not have a bad focus factor, it has an unnamed overhead that belongs in the itemized list above. The factor is meant to cover residue, not to hide a standing meeting.

      How much time do engineers spend in meetings?

      Commonly 4 to 8 hours a week for individual contributors, and materially more for leads, staff engineers, and anyone attached to more than one team. Do not estimate this one. Export the team calendar, count recurring events, and use the real figure. It is the largest deduction in this calculator for most teams and the only one you can cut this week.

      Should on call count against sprint capacity?

      Yes, and treating it as free is how rotations quietly become punishment. The engineer holding the pager is doing real work that no board reflects, and their planned work is what slips when an incident lands. Model it as a percentage of their sprint, then reduce the percentage by fixing the alerts rather than by asking them to try harder.

      My team estimates in ideal days already. Am I double counting?

      You would be, yes. Ideal-day estimates already assume uninterrupted work, which is the same discount the focus factor applies. Pick one: either estimate in raw effort and keep the focus factor at 70%, or estimate in ideal days and push the focus factor up to 90%. Applying both is how a team ends up committing to about half of what it could actually do, then wondering why the roadmap slipped.

      Once you know what the sprint is really worth, the next argument is usually about what to spend it on. What should AI do here? assesses one workflow at a time and will tell you to leave it alone when that is the right answer.